DAY 12, 20 APR 2010 (Tuesday)
A quiet day at the office. The bosses were having their meeting with the people from JKR regarding the progress of the construction here. I went around observing the works being carried out at the site.

DAY 13, 21 APR 2010 (Wednesday)
Bosses had their second day of meetings with the JKR people. I observed the installation of additional lighting protection for the i-supervision towers.

The copper rod to which the copper wire is attached to goes down to a depth of about 30 feet (9 metres).

DAY 14, 22 APR 2010 (Thursday)
Observed installation of first floor pre-cast floor slabs.

Some of the perils of working at a construction site:

DAY 15, 23 APR 2010 (Friday)
Assisted in office work and translation of documents from BM to English.